Airfield Lighting Designers

AGL designs can be performed for all military and civilian aerodrome types from regional non-instrument runways to full CAT IIIB hub airport runways. We can provide full AGL designs whether or not a project specification is available, by defining the design criteria. AGL Designs can be provided in one of all of the stages from concept, detailed design, for construction and as-constructed.


All Airfield Lighting designs fully comply to the relevant international and national regulatory bodies such as ICAO, IEC, EASA, STANAG, ACI, FAA, CAA, CASA, CAAS, GCAA and IAA.


Our AGL Design services include:

  • AGL Design and Drawings Review
  • AGL Concept Design
  • Detailed Design
  • AGL Pit and Ducts locations
  • Shop Drawings
  • As-Built Drawings
  • AGL Design Document
  • Final Bill Of Quantities
  • Design Calculations
  • CCR Calculations
  • PAPI Locations
  • Approach Lighting Profile
  • Heliport Lighting Design

AGL DESIGN PROJECT LIST






Client:          Waterford Airport

Project:        03-21 Runway Extension

Location:     Waterford Airport

Service:       AGL Concept Design

Timeline:    March 2020 - Present



Client:           Brooklyn Engineering Services

Project:         Approach 16 Cable Diversion

Location:      Dublin Airport

Service:         AGL Design Report

Timeline:      January - February 2019



Client:           Airways New Zealand

Project:         Flexible Contingent Runway

Location:      Auckland Airport

Service:         AGL Drawing Review

Timeline:      August 2018



Client:            Vinci (VCGP)

Project:          Airport Development Plan 2025

Location:       Belgrade Airport

Service:         AGL Concept Design and BOQ

Timeline:       April - August 2018



Client:           Perfect Airport Solutions

Project:         NSC Packages 1 & 2 AGL CMS

Location:      Singapore Changi Airport

Service:         CMS Equipment Drawings

Timeline:      May 2017 – October 2017



Client:           Avionics Limited

Project:         11/29 Runway Circuit Upgrade

Location:      Darwin Airport

Service:         AGL Design Services

Timeline:      May 2017 – October 2017



Client:           Perfect Airport Solutions

Project:         NSC Package 2  (02C-20C)

Location:      Singapore Changi Airport

Service:         AGL Designer

Timeline:      October 2016 - August 2017



Client:           ADB SAFEGATE

Project:         AGL and NC Backup Runway

Location:      Taiwan Taoyuan Airport

Service:         AGL Design

Timeline:      July - December 2013








Client:          Waterford Airport

Project:        03-21 AGL Upgrade Works

Location:     Waterford Airport

Service:       AGL Design and Consultant

Timeline:    July 2012 - August 2013



Client:           Dublin Airport Authority

Project:         Taxiway CL and Stop Bar lighting

Location:      Cork Airport

Service:         AGL Design and Site Supervision

Timeline:      June - December 2012



Client:           Dublin Airport Authority

Project:         Aerlingus Pier B Accommodation

Location:      Dublin Airport

Service:         Tender Package and Drawings

Timeline:      March - July 2012



Client:           Dublin Airport Authority

Project:         Remote Parking Floodlighting

Location:      Shannon Airport

Service:         Tender Package and Drawings

Timeline:      January - April 2012



Client:           Dublin Airport Authority

Project:         17-35 Rehabilitation

Location:      Cork Airport

Service:         AGL Design and Tender Package

Timeline:      January 2012



Client:           Dublin Airport Authority

Project:         16-34 - CAT I Stop Bars

Location:      Dublin Airport

Service:         AGL Design and Tender Package

Timeline:      December 2011 - July 2012



Client:           Dublin Airport Authority

Project:         Standby Generator Replacement

Location:      Dublin Airport

Service:         Drawings and Supervision

Timeline:      December 2011 - July 2012



Client:           Dublin Airport Authority

Project:         Taxiway A Rehabilitation

Location:      Shannon Airport

Service:         Tender Documents

Timeline:      May - December 2011



Client:           Dublin Airport Authority

Project:         TBG Removal - AGL and HML

Location:      Dublin Airport

Service:         AGL Design and Supervision

Timeline:      May - October 2011



Client:           Dublin Airport Authority

Project:         TCL and Stop Bar Upgrades

Location:      Dublin Airport

Service:         AGL Design and Drawings